City of Placerville Fair Lane Construction Update

by Placerville Newswire / Sep 24, 2016 / comments

The working hours westbound lane closure of Fair Lane from Denny's will extend past Juvenile Hall beginning the week of September 26th.

This is a weekly update to the community regarding the Western Placerville Interchanges Phase 1B Project.  

Construction began Tuesday, September 6th. 

Prior Week:
>Demolition, including roadway excavation, continued into this week. 
>Subgrade for the new curb, gutter, and sidewalk was prepared. 
>Conduit installation for the street lights began later in the week. 

Current Week:
>Complete conduit installation for the street lights. 
>Finish subgrade for the new curb, gutter, and sidewalk. 
>Begin placing AB for the new curb, gutter, and sidewalk. 

Following Week:
>Finish placing AB and begin forming work for the new curb, gutter, and sidewalk. 
>Concrete may be poured later in the week. 
>Clearing, grubbing, and tree removal for the second stage of construction may begin later in the week. 

Important Information:
>During the first stage of construction the westbound lane between Juvenile Hall and Denny’s will be closed during working hours. 
>The second stage of construction will begin the week of September 26th and the westbound lane closure will extend past Juvenile Hall. 
>Please note that starting October 3rd and lasting until the beginning of December, a portion of Fair Lane will be closed 24‐hrs a day for Stage 2 construction.
>Please adjust your travel routes accordingly.  At least one driveway to each parking lot will be open at all times. 

Contacts:
Jim Fisher, Resident Engineer   R.E.Y. Engineers  (916) 612‐7581  jfisher@reyengineers.com 
Ryan Ruddick, Inspector    R.E.Y. Engineers  (707) 391‐7013  rruddick@reyengineers.com 
Rebecca Neves, City Engineer  City of Placerville  (530) 642‐5250  rneves@cityofplacerville.org